Acid Plant Bund Refurbishment

Husab Uranium Mine, Arandis

6077

The work involved the demolition and reconstruction of the Acid Plant primary bunded area, due to acid penetration and reaction with the substrate. Most of the work had to be done by hand due to proximity of nearby equipment. The work was completed in a partnership with Industrial Acid Proofing Namibia, who executed the acid-proofing on the concrete.

    CLIENT: Swakop Uranium CGNPC / IAP Namibia

    COMPLETION: October 2019

    You are currently viewing Acid Plant Bund Refurbishment