Husab Uranium Mine, Arandis
6301
Emergency work was required to stabilise a Rockbreaker platform at the Primary Input crusher. Ablecon was tasked to design and construct this expanded and strengthened base during a limited shutdown period of 72 hours. After a monitoring period it was decided to add additional bolting for
further redundancy.
CLIENT: Swakop Uranium CGNPC
COMPLETION: October 2022